Town of Castle Rock Plum Creek Diversion Pump Station
Owner:
Town of Castle Rock
Engineer:
Dewberry
Project Description:
Traditional Bid
Cost: $9,365,645
Project Description
The project generally consists of construction of a new raw water pump station. The diversion pump station is designed to pump 26 MGD from Plum Creek up to Castle Rock Reservoir 1. Additional pumps are designed to pump 8 MGD of raw water from Castle Rock Reservoir 1 back to the Town of Castle Rock. The project included the installation of approximately 2,500 feet of 30 inch pipe. RN Civil will self-performed over 70% of the work.
The largest pumps on the project were 500hp!